Ford Field

ford-fieldGreat Lakes Geomatics was asked to establish horizontal and vertical control for the site, and provide layout for the prime contractor and other on-site trades. We provided staking for mass grading, caissons, foundations, anchor bolts, steel, precast concrete, walls, statues, seating, signs, water main, sewers, plumbing, etc.

We performed as-built surveys for QA/QC of the design build portions and other purposes for the prime contractor. In addition, we were responsible for creating easements and street vacation documents for the project. Our technicians had the primary function to create a full As-Built and monitor 200 ton steel trusses that were constructed on-site to ensure they would meet design criteria.

GREAT LAKES GEOMATICS can support your project with complete land surveying, laser scanning services, and UAV (drone) services. 

Call us today at (586) 755-5770.